BUS 375 MS Project Familiarization Assignment
1-Strayer
Assignment 1 MS Project Familiarization
Due Week 3 and worth 90 points
Prior to completing the assignment, be sure to
review the selected MS Project tutorial videos located in Week 2 of the
Blackboard online course.
Write a two to three (2-3) page paper in which
you summarize your thoughts on Microsoft Project:
Give your opinion on how easy or difficult MS
Project seems to be from a user experience standpoint.
Suggest at least two (2) challenges you
foresee in using MS Project in this course.
Describe why it is important to use a tool
like MS Project instead of using other tools (e.g., MS Word, MS Excel) to
manage and track your schedule.
Format your assignment according to the
following formatting requirements:
Typed, double spaced, using Times New Roman
font (size 12), with one-inch margins on all sides.
Include a cover page containing the title of
the assignment, the student’s name, the professor’s name, the course title, and
the date. The cover page is not included in the required page length.
BUS 375 Project Proposal Assignment 2-Strayer
Assignment 2 Project Proposal
Due Week 6 and worth 150 points
You have been selected to be the project
manager (for a project of your choice). The project you choose here will be used
again in Assignment 4 (Week 6) and you may be asked to reference this project
in subsequent weekly discussions. The project that you decide to use should
meet the key criteria of a project, such as (a) having a beginning and an end;
(b) results in something being delivered to someone; (c) requires a series of
activities that must be done to complete the project; and (d) requires
resources (e.g, people, materials) to complete the work. The project can be one
of a personal or professional nature.
Write a two to three (2-3) page paper in which
you define the scope of your chosen project. In your paper you must:
Provide a brief summary of your chosen
project.
Describe at least three (3) project goals and
three (3) project objectives.
Identify the key customer(s) and at least two
(2) stakeholders for your project. Remember, you are delivering the project to
your customer(s); however, there are others (stakeholders) who have a vested
interest in your project.
Describe at least three (3) key milestones and
/or deliverables for your project.
Describe a high-level timeline that includes
key tasks and deadlines.
Estimate the project’s overall cost and any
key staffing and non-staffing resources needed.
Examine your project’s greatest challenge and
provide a recommendation for addressing the challenge in question.
Typed, double spaced, using Times New Roman
font (size 12), with one-inch margins on all sides.
Include a cover page containing the title of
the assignment, the student’s name, the professor’s name, the course title, and
the date. The cover page is not included in the required page length.
Grading for this assignment will be based on
answer quality, logic/organization of the paper, and language and writing
skills, using the following rubric:
|
Points: 150
|
Assignment 2:
Project Proposal
|
||||
|
Criteria
|
Unacceptable
Below 60% F
|
Meets Minimum
Expectations
60-69% D
|
Fair
70-79% C
|
Proficient
80-89% B
|
Exemplary
90-100% A
|
|
1. Provide a brief
summary of your chosen project.
Weight: 12%
|
Did not submit or
incompletelyprovided a brief summary of your chosen project.
|
Insufficiently
provided a brief summary of your chosen project.
|
Partially provided a
brief summary of your chosen project.
|
Satisfactorily provided
a brief summary of your chosen project.
|
Thoroughly provided
a brief summary of your chosen project.
|
|
2. Describe at least
three (3) project goals and three (3) project objectives.
Weight: 13%
|
Did not submit or
incompletelydescribed at least three (3) project goals and three (3) project
objectives.
|
Insufficiently
described at least three (3) project goals and three (3) project objectives.
|
Partially described
at least three (3) project goals and three (3) project objectives.
|
Satisfactorily
described at least three (3) project goals and three (3) project objectives.
|
Thoroughly described
at least three (3) project goals and three (3) project objectives.
|
|
3. Identify the key
customer(s) and at least two (2) stakeholders for your project.
Weight: 13%
|
Did not submit or
incompletelyidentified the key customer(s) and at least two (2) stakeholders.
|
Insufficiently
identified the key customers and at least two (2) stakeholders.
|
Partially identified
the key customers and at least two (2) stakeholders.
|
Satisfactorily
identified the key customers and at least two (2) stakeholders.
|
Thoroughly
identified the key customers and at least two (2) stakeholders.
|
|
4. Describe at least
three (3) key milestones and /or deliverables for your project.
Weight: 13%
|
Did not submit or
incompletelydescribed at least three (3) key milestones and /or deliverables
for your project.
|
Insufficiently
described at least three (3) key milestones and /or deliverables for your
project.
|
Partially described
at least three (3) key milestones and /or deliverables for your project.
|
Satisfactorily
described at least three (3) key milestones and /or deliverables for your
project.
|
Thoroughly described
at least three (3) key milestones and /or deliverables for your project.
|
|
5. Describe a high-level
timeline that includes key tasks and deadlines.
Weight: 13%
|
Did not submit or
incompletelydescribed a high-level timeline that includes key tasks and
deadlines.
|
Insufficiently
described a high-level timeline that includes key tasks and deadlines.
|
Partially described
a high-level timeline that includes key tasks and deadlines.
|
Satisfactorily
described a high-level timeline that includes key tasks and deadlines.
|
Thoroughly described
a high-level timeline that includes key tasks and deadlines.
|
|
6. Estimate the
project’s overall cost and any key staffing and non-staffing resources
needed.
Weight: 13%
|
Did not submit or
incompletelyestimated the project’s overall cost and any key staffing and
non-staffing resources needed. |
Insufficiently
estimated the project’s overall cost and any key staffing and non-staffing
resources needed.
|
Partially estimated
the project’s overall cost and any key staffing and non-staffing resources
needed.
|
Satisfactorily
estimated the project’s overall cost and any key staffing and non-staffing
resources needed.
|
Thoroughly estimated
the project’s overall cost and any key staffing and non-staffing resources
needed.
|
|
7. Examine your
project’s greatest challenge and provide a recommendation for addressing the
challenge in question.
Weight: 13%
|
Did not submit or
incompletelyexamined your project’s greatest challenge and did not submit or
incompletely provided a recommendation for addressing the challenge in
question.
|
Insufficiently
examined your project’s greatest challenge and insufficiently provided a
recommendation for addressing the challenge in question.
|
Partially examined
your project’s greatest challenge and partially provided a recommendation for
addressing the challenge in question.
|
Satisfactorily
examined your project’s greatest challenge and satisfactorily provided a
recommendation for addressing the challenge in question.
|
Thoroughly examined
your project’s greatest challenge and thoroughly provided a recommendation
for addressing the challenge in question.
|
|
8. Clarity, writing
mechanics, and formatting.
Weight: 10%
|
More than 8 errors
present
|
7-8 errors present
|
5-6 errors present
|
3-4 errors present
|
0-2 errors present
|
BUS 375 Greendale Project ReDux Assignment
3-Strayer
Assignment 3 Greendale Project ReDux
Due Week 8 and worth 90 points
This assignment consists of two (2) parts: a
project schedule, and a written response. You must submit both parts as
separate files for the completion of this assignment. Label each file name
according to the part of the assignment it is written for.
Part A: Project Schedule
(Submit as one [1] Microsoft Project file)
Create a multi-level work breakdown structure
(WBS) and detailed project schedule, using the information from the “Greendale
Stadium Case” located at the end of Chapter 6, and incorporating the following
constraints.
Note: When you create your MS Project
schedule, you will need to update your project per the following constraints:
The project must consist of at least twenty
(20) tasks.
Each task must have a start and finish date
that matches the duration noted in the assignment.
Each task must be assigned to a resource
(e.g., Demolishing Crew; Construction Crew; Landscaping Crew).
Assume that the crew works during normal
weekdays (no weekend work) under normal conditions (8 hours per day).
In terms of holidays, you can assume no work
will be done the following days: New Year’s Day, President’s Day, Good Friday,
Good Monday, Friday before Memorial Day, Memorial Day, the business day before
Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the
day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after
Thanksgiving), the business day before Christmas, Christmas Day, the business
day after Christmas Day, and New Year’s Eve.
Part B: Written Response
(Submit as a Microsoft Word file)
Respond to the following questions in a one to
two (1-2) page paper based on your project schedule.
When will the project be completed?
What is the critical path for the project?
How much slack / float is in your project?
What activities have the greatest slack / float?
Identify the top three (3) activities that you
believe could impact the project completion date.
What additional activities you would add to
this project to make it more complete, from a project management viewpoint?
Format your assignment according to the
following formatting requirements:
Typed, double spaced, using Times New Roman
font (size 12), with one-inch margins on all sides.
Include a cover page containing the title of
the assignment, the student’s name, the professor’s name, the course title, and
the date. The cover page is not included in the required page length.
Grading for this assignment will be based on
answer quality, logic/organization of the paper, and language and writing
skills, using the following rubric.
|
Points: 90
|
Assignment 3:
Greendale Project ReDux
|
||||
|
Criteria
|
Unacceptable
Below 60% F
|
Meets Minimum
Expectations
60-69% D
|
Fair
70-79% C
|
Proficient
80-89% B
|
Exemplary
90-100% A
|
|
Part A: Project
Schedule
|
|||||
|
1a. Create a
multi-level work breakdown structure (WBS) and detailed project schedule,
using the information from the “Greendale Stadium Case” located at the end of
Chapter 6, and incorporating the stated constraints.
Weight: 55%
|
Did not submit or
incompletely created a multi-level work breakdown structure (WBS) and
detailed project schedule, using the information from the “Greendale Stadium
Case” located at the end of Chapter 6, and incorporating the stated
constraints.
|
Insufficiently
created a multi-level work breakdown structure (WBS) and detailed project
schedule, using the information from the “Greendale Stadium Case” located at
the end of Chapter 6, and incorporating the stated constraints.
|
Partially created a
multi-level work breakdown structure (WBS) and detailed project schedule,
using the information from the “Greendale Stadium Case” located at the end of
Chapter 6, and incorporating the stated constraints.
|
Satisfactorily
created a multi-level work breakdown structure (WBS) and detailed project
schedule, using the information from the “Greendale Stadium Case” located at
the end of Chapter 6, and incorporating the stated constraints.
|
Thoroughly created a
multi-level work breakdown structure (WBS) and detailed project schedule,
using the information from the “Greendale Stadium Case” located at the end of
Chapter 6, and incorporating the stated constraints.
|
|
Part B: Written
Response
|
|||||
|
1b. Respond to the
stated questions in a one to two (1-2) page paper based on your project
schedule.
Weight: 40%
|
Did not submit or
incompletely responded to the stated questions in a one to two (1-2) page
paper based on your project schedule.
|
Insufficiently
responded to the stated questions in a one to two (1-2) page paper based on
your project schedule.
|
Partially responded
to the stated questions in a one to two (1-2) page paper based on your
project schedule.
|
Satisfactorily
responded to the stated questions in a one to two (1-2) page paper based on
your project schedule.
|
Thoroughly responded
to the stated questions in a one to two (1-2) page paper based on your
project schedule.
|
|
2b. Clarity, writing
mechanics, and formatting.
Weight: 5%
|
More than 8 errors
present
|
7-8 errors present
|
5-6 errors present
|
3-4 errors present
|
0-2 errors present
|
BUS 375 Project Schedule Assignment 4-Strayer
Assignment 4 Project Schedule
Due Week 10 and worth 150 points
This assignment consists of two (2) parts: a
project schedule, and a written response. You must submit both parts as
separate files for the completion of this assignment. Label each file name
according to the part of the assignment it is written for.
Part A: Project Schedule
(Submit as one [1] Microsoft Project file)
In Assignment 2, you developed a project plan.
Now, using the information from your project proposal, create a multi-level
work breakdown structure (WBS) and detailed project schedule.
Your project must include the following
criteria:
The project must consist of at least
twenty-five (25) tasks.
Each task must contain a start date, a finish
date, and have main staffing and non-staffing resources assigned.
Assume that your work activities are completed
during normal weekdays (no weekend work) under normal conditions (8 hours per
day).
In terms of holidays, you can assume no work
will be done the following days: New Year’s Day, President’s Day, Good Friday,
Good Monday, Friday before Memorial Day, Memorial Day, the business day before
Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the
day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after
Thanksgiving), the business day before Christmas, Christmas Day, the business
day after Christmas Day, and New Year’s Eve.
Part B: Written Response
(Submit as a Microsoft Word file)
Write a one to two (1-2) page response in
which you:
Analyze your project in terms of project
completion, critical path, and slack / float. Specifically, be sure to answer
the following:
When will the project be completed?
What is the critical path for the project?
Summarize the recommendations or improvements
you would make to your project schedule. Specifically, be sure to answer the
following:
Identify the top three (3) activities that you
believe could impact the project completion date.
What additional activities would you add to
this project to make it more complete, from a project management viewpoint?
Format your assignment according to the
following formatting requirements:
Typed, double spaced, using Times New Roman
font (size 12), with one-inch margins on all sides.
Include a cover page containing the title of
the assignment, the student’s name, the professor’s name, the course title, and
the date. The cover page is not included in the required page length.